LMS Implementation Project Plan - Sample

<< Click to Display Table of Contents >>

Navigation:  Getting started >

LMS Implementation Project Plan - Sample

Sample LMS Implementation Plan

A few things to remember before you get started.

Define a project manager and assign roles and responsibilities to the rest of the team.

Start with the basics. Don’t plan to use all of the advanced features until the team is fully familiar with the LMS.

Create a communication plan. From pilot and key stakeholders, the team should get ideas on how to communicate and market the LMS to the broader audience. 

Think about the kind of materials that should be developed to help the users move around the LMS when it is officially launched.

Document each decision! It’s important to have a Data Entry Standards document to keep track of the decisions made.

Also document the goals for the LMS.  That way you can refer back to them if you feel the project gets off track. 

Take your time. Do not rush the implementation!

 

Important!

Any task that may take a few hours, has been allocated 1 working day in the sample below. It’s unlikely to take the entire day!

Task

Who’s Responsible

Allocated Time

Start Date

End Date

Getting Started Call – Discuss implementation plan, rollout dates, pilot, desired go live dates, roles & responsibilities etc

Intellek & the Client’s Training Team

30 mins - 1 hour

 

 

Intellek to create an LMS training sandbox for testing and training purposes (30 - 90 days access)

Intellek

1 working day

 

 

LMS Training

Intellek & the Client’s Training Team

4 x 90-minute sessions scheduled over a week to 10 days.

 

 

Intellek to create a live LMS instance.

Intellek  

1 – 2 working days

 

 

Publish Intellek Courses to live LMS instance

Intellek

1 -2 working days

 

 

Review the Security Profiles available and decide who in the firm will get what access

Client’s Training Team

Up to ½ day

 

 

Populate the Import Learners Spreadsheet or provide data via the API  

Intellek, the Client’s Training Team/HR & IT/Tech Team

1 – 2 working days, over the period of a week or two. Dependant on quality of data

 

 

Setup Automated Learner Data Feed

Intellek & Client’s IT/Tech Team

1 working day

 

 

Setup Single Sign-On

Intellek & Client’s IT/Tech Team

1 working day

 

 

Assign the correct Event Contact Type to the necessary Trainers, Speakers etc.

Client’s Training Team

30 mins - 1 hour max!

 

 

Discuss and create commonly used Groups

Client’s Training Team

½ day – 2 working days, depending on how many

 

 

Discuss and create Categories and Subcategories

Client’s Training Team

½ - 1 working day, depending on how many

 

 

Upload existing Training Resources and any existing eLearning Courses you have

Client’s Training Team

½ - 2 working days, depending on how many and whether you use manual or bulk import

 

 

Review Locations and assign the correct Time Zone

Client’s Training Team

½ working day

 

 

Create Venues for each Location

Client’s Training Team

½ - 1 working day

 

 

Add Scheduled Courses to the Course Catalogue

Client’s Training Team

Up to a week, depending on how many

 

 

Populate Training News

Client’s Training Team

½ - 1 working day

 

 

Customize Email Templates

Client’s Training Team

½ – 2 working days, depending on the customizations

 

 

Schedule Classes on the Calendar

Client’s Training Team

On the assumption, you’d start with one month’s training on the calendar, I’d allow a week to get everything scheduled.  

 

 

Create Learning Paths

Client’s Training Team

½ - 2 working days, depending on how many

 

 

Create any Surveys/Feedback forms

Client’s Training Team

Allow 1 working day for the creation of two surveys, dependant on how long they are.

 

 

Go Live!

Client’s Training Team

N/A!